BILL ANALYSIS
SENATE COMMITTEE ON AGRICULTURE AND WATER RESOURCES
Jim Costa, Chairman
SB 553 (Kelley)
As Amended March 25, 1999
Hearing Date: April 20, 1999
Fiscal: Yes
Consultant: Dan Webb
PURPOSE OF BILL:
To mandate annual progress reports to the Legislature on
construction of the Inland Feeder Project of the Metropolitan
Water District of Southern California.
BACKGROUND:
Metropolitan Water District of Southern California is in the
process of building the Inland Feeder Project, consisting of 44
miles of 12-foot diameter tunnels and pipelines to provide an
eastern connection between the State Water Project terminus at
Lake Silverwood and the Colorado River Aqueduct south of Lake
Perris. Total project costs are anticipated in the $1.2 billion
range.
PROPOSED LAW:
This bill would require Metropolitan Water District of Southern
California to submit to the Legislature an annual progress
report on the Inland Feeder Project. Incepting February 1,
2000, the report would include a description of progress, a log
of expenses, and variations between budgeted and actual costs.
Costs for the report are not to exceed $50,000.
COMMENTS:
This bill mirrors SB 552 by the same author, a mandated report
on Metropolitan's Eastside Reservior. Because the report
requirement in this bill is an annual expense, some
clarification is needed as to whether the report cost cap of
$50,000 is to be an annual or cumulative maximum.
SUPPORT:
None
OPPOSED:
None